BKL has made a significant contribution to the understanding and control of noise and vibration from the Vancouver Light Rail Transit (LRT) system. The following are past completed projects:

Evergreen SkyTrain Line

Environmental noise and vibration assessment to Canada Environmental Assessment Act (CEAA) standards for 11 km SkyTrain line connecting Coquitlam Town Centre and Port Moody to the Millennium Line, with above grade, at-grade and tunnel sections. Included comprehensive characterization of existing SkyTrain noise and vibration using measurements at heights above and below active Millennium Line guideways, with and without noise barriers, for three generations of vehicles. Baseline monitoring and detailed noise and vibration predictions for both construction and operations phases. Drafted specifications for vehicle noise and station acoustics. Extensive public consultation and stakeholder engagement.

Common Acoustical Challenges:

  • Wayside noise and vibration
  • Guideway noise barriers
  • Station acoustics and platform communications
  • Underground station ventilation noise
  • Vehicle noise specifications
  • Developments next to transit lines

Evergreen LRT Line

Environmental impact assessment of the at-grade alignment for the proposed LRT line connecting Coquitlam and Port Moody to the Millennium Line at Lougheed Mall.

Canada Line

Environmental noise and vibration assessment, detailed design and construction noise management for the LRT line connecting Richmond Town Centre, Vancouver International Airport and downtown Vancouver. Vehicle noise specifications. Acoustical design for both above ground and underground stations. Assessment and control of underground station ventilation noise.

SkyTrain Millennium Line

Assessment of SkyTrain noise and vibration impact on the Lougheed corridor from Glen Avenue to North Mall, continuing on the Brunette Columbia corridor to Columbia Station. Participation in open houses to provide guidance to the community about SkyTrain noise issues. Design of guideway noise barriers and field testing to confirm their effectiveness.

SkyTrain PMC Line

Assessment of noise impact significance for alternative routes on the SkyTrain extension proposed from Lougheed Mall to Coquitlam Town Centre.

Vancouver/Richmond Rapid Transit Corridor Study

Development of evaluation criteria for community noise impact from three alternative rapid transit technologies (ALRT, Bus and Rail) for several proposed corridors from Vancouver to Richmond.

Gateway Station

Evaluation of the potential impact of the proposed Gateway Station on their Gateway Integrated Development involving both commercial and residential facilities as well as outdoor public malls.

Provided a later evaluation of the significance of acoustical treatment to the ceiling and roof of the proposed Gateway Station to improve platform communications and reduce the disturbance potential of rain on the platform roof.

SkyTrain Track Lubricant Study

A study of the acoustical benefits of a proprietary wheel/rail lubricant system.

Numerous studies on the original SkyTrain system from Waterfront to New Westminster Stations including:

  • Prediction of Noise and Vibration Levels Adjacent to Proposed SkyTrain Line
  • Dunsmuir Tunnel Vibration Survey
  • Vancouver SkyTrain Baseline Noise and Vibration Survey Measurement Sites
  • Noise Control on SkyTrain Electrical Substation
  • SkyTrain Station Design Manual – Acoustics
  • Acoustical Design of SkyTrain Stations

Residential Developments Adjacent to LRT Lines

BKL has been retained on many occasions to assess the potential effects of LRT noise on developments proposed for locations close to the right of way, including recommendations to improve building envelope sound isolation, where warranted.

Words From Our Clients

“During the planning stage of the Evergreen Line Rapid Transit Project, BKL was instrumental. Their work was completed to a high professional standard, and was delivered on time and within budget.”

R. Scott Hanna

formerly Senior Environment Manager at Evergreen Line Rapid Transit Project

Featured Case Study

Evergreen Line Skytrain Extension

Evergreen Line Skytrain Extension

Stretching from Coquitlam to Burnaby, the Evergreen Line opened in December 2016. It's the latest extension to Metro Vancouver's SkyTrain system, the longest fully-automated, driverless rapid-transit system in the world. The Evergreen Line includes seven stations and 11 kilometres of track—with underground, ground level, and raised sections. The extension connects to the existing Millennium Line, so residents of Coquitlam, Port Coquitlam, and Port Moody can travel to downtown Vancouver without having to transfer. This easy connection, combined with the frequency of the trains—running every three minutes during peak hours—makes Evergreen a fast and convenient public transit option, something planners hope will take as many as 40,000 cars off the road by 2021. BKL joined the project in 2008, and the firm's first task was to establish baseline noise and vibration levels along the alignment and conduct a noise and vibration impact assessment as part of the project's application for an environmental assessment certificate. BKL designed a thorough baseline monitoring program that included 48-hour community noise monitoring at 22 locations along the alignment and short-term vibration monitoring at another five locations. BKL also performed detailed measurements of SkyTrain noise and vibration along the operational Millennium Line to define source-specific factors such as guideway structure reflection and shielding effects and guideway noise barrier performance at different heights. BKL's next step was developing a comprehensive noise and vibration prediction model for the project. Using preliminary design information, road and rail traffic forecasts, proposed construction methods, and data gathered during the baseline and SkyTrain monitoring programs, BKL built a 3-D computer model to develop noise maps at the first two rows of housing along the entire 11 kilometre extension, an area that includes 1,044 dwellings. BKL developed noise maps along the 11 kilometre extension—including 1,044 dwellings. The model applied best practice standards to predict how noise levels would change during the construction and operations phases. It also showed which residences would likely be affected by construction noise and/or operational noise from the trains and stations. Additionally, BKL developed a vibration-prediction model covering more than 600 buildings. This model mapped areas where construction activities (e.g., tunnel boring) and SkyTrain traffic had the potential to create significant impacts. With the possible noise and vibration trouble-spots identified, BKL worked closely with the BC Ministry of Transportation and Infrastructure and its private sector partners to develop requirements for cost-effective SkyTrain-specific mitigation options, and modelled each option to show its benefits and limitations. BKL participated in extensive open-house consultation and, throughout the duration of the environmental assessment, responded to inquiries from reviewing agencies and the public. BKL's report was prepared to Canadian Environmental Assessment Act (CEAA) standards. BKL also developed acoustical performance specifications for the trains, stations, and ancillary equipment to improve comfort and communication for the passengers while avoiding creating additional community noise impacts. During construction, BKL provided advice on an as-needed basis to mitigate construction noise impacts. Once construction was complete, BKL carried out a post-construction monitoring program to check operational noise and vibration levels. It included 72-hour noise monitoring at 30 locations in the community and short-term vibration monitoring at another eight locations. BKL compared these noise levels against thresholds defined in the project's environmental assessment certificate table of commitments. BKL's contributions to the project were recognized by R. Scott Hanna, who was Senior Environment Manager for the project's environmental assessment. Hanna said the following: "During the planning stage of the Evergreen Line Rapid Transit Project, BKL was instrumental in determining ambient noise conditions along the proposed alignment, assessing potential noise and vibration impacts of the project and developing workable and cost-effective mitigation measures, as part of the environmental impact assessment (EIA). Their work was completed to a high professional standard, and was delivered on time and within budget." Have a project in mind? Get in touch today.